The 5 stages of activewear production

This guide walks through the stages a real activewear line goes through, in the order most brands experience them. Timelines assume a US factory — overseas runs roughly double the timeline.

Stage 1: Tech pack (1–2 weeks)

Before any fabric is cut, your tech pack needs to be finished. A complete tech pack covers:

  • Sketches (front, back, side, detail callouts)
  • A measurement spec for every size in your run
  • Fabric composition, weight (GSM), stretch percentage
  • Stitch types and seam constructions
  • Pantone colors for every fabric, trim, and label
  • Label placements (size, care, brand)

If you can hand this to a factory and they have zero follow-up questions, your tech pack is in good shape.

Stage 2: Sampling (3–6 weeks)

A typical activewear line goes through 3 sample rounds before the first production run:

  • Round 1 (proto): proves the pattern works. Expect sizing issues, fabric weight surprises, and the occasional seam placement do-over.
  • Round 2 (fit sample): adjusted based on Round 1 feedback. Usually gets you 80% of the way.
  • Round 3 (pre-production sample / PPS): the sample you sign off on before bulk production starts. This is the one you keep.

Budget 50–00 per sample, depending on complexity. Some LA factories credit sample costs against your first production run.

Stage 3: Pre-production (2–4 weeks)

Once the PPS is approved:

  • Fabric is ordered — MOQs at the fabric supplier usually run 50–200 yd per color
  • Trims are ordered — elastics, zippers, labels, tags
  • Patterns are graded — your size run is generated from the base size
  • A marker is laid — the pattern pieces are arranged on fabric to minimize waste

This is also when you confirm the production price in writing, lock the deposit terms, and set the production start date.

Stage 4: Bulk production (4–8 weeks)

For an LA factory, a 100–300 unit run usually takes 4–6 weeks. A 500+ unit run takes 6–8 weeks. The factory will:

  • Cut all units in a single cut for color consistency
  • Sew in waves (typically 30–50 units per day for an experienced crew)
  • Do in-line quality checks during sewing, not just at the end
  • Press, fold, and pack per your spec

Stage 5: QC + delivery (1 week)

Before anything ships, expect a final inspection. Most factories pull 10–20% of finished units and check against the spec. Common catches:

  • Stitching skipped in tight areas (under arms, gussets)
  • Slight color variation between dye lots
  • Labels in the wrong position

A reliable LA factory will fix these before shipping, not after.

Total realistic timeline

For a first-time brand launching a 4–6 style activewear capsule:

  • Tech pack: 2 weeks
  • Sampling: 4 weeks
  • Pre-production: 3 weeks
  • Bulk production: 6 weeks
  • QC + delivery: 1 week
  • Total: ~16 weeks (4 months)

An experienced brand with a tech pack ready can shave 4–6 weeks off this.

What it costs

Rough per-unit costs for LA activewear manufacturing:

  • Leggings: 8–5 per unit at 100+ qty
  • Sports bras: 4–8 per unit at 100+ qty
  • Tanks / tees: 0–2 per unit at 100+ qty
  • Hoodies / jackets: 8–5 per unit at 100+ qty

Prices include fabric from the factory's standard line. Custom fabric, dye lots, or trim will add cost.

Common mistakes first-timers make

1. Underestimating fabric MOQs. If your run is small, fabric minimums may dictate the price, not the labor.
2. Skipping the PPS. Without a pre-production sample, you are gambling on the bulk run.
3. Booking marketing before the samples are right. Re-shooting a launch is expensive.

Working with an LA manufacturer

Los Angeles factories are ideal for activewear because the fabric, trim, and pattern-making supply chain is concentrated here. Lead times are short and you can walk the factory floor.

*Have a tech pack ready? Reach out for a sample quote and a realistic timeline.*